WHAT MATTERED TO ME
The snagging list—and later discoveries
My January 2024 snagging list contained 300-plus observations, varying in seriousness. Later removal of trims or internal sills revealed additional concealed issues. None of the first-floor windows has been assessed externally because of the height, so both the original list and subsequent checks remain substantially incomplete in their coverage.
What the January 2024 list covered
I supplied this room-by-room list at T&K’s request on 30 January 2024. It covered the concerns known to me then, before the later discoveries behind trims:
- Opening, closing and hardware: Problems with operation, fittings and components.
- Frame alignment and positioning: Frames reported as leaning or sitting unevenly within openings.
- Seals and draughtproofing: Missing, disturbed or poorly finished seals and perimeter joints.
- Glass and sealed units: Scratches, marks, trapped material and concerns about how units were fitted.
- Trims and internal finishes: Wide or built-up trims, awkward sill junctions and uneven finishing.
- Damage and making good: Plaster, render, decoration, tiles and surrounding surfaces.
- Cleaning, missing items and checks: Debris, surface marks, missing equipment and areas still requiring inspection.
This was a non-exhaustive historical list of my observations, including areas needing inspection. It is not a reconciled count of separate defects still outstanding today. T&K disputed my assessment and declared completion in November 2024; the chronology records the correspondence that followed.
01First-floor exteriors remain unassessed
None of the first-floor windows has been assessed externally because of the height. The original snagging list and subsequent checks therefore leave a substantial part of the installation unassessed. The full extent of any external issues at first-floor level remains unknown.
02Concern about what remains hidden
Every area I have opened up and checked has revealed an issue I consider serious. I’m concerned these discoveries may be the tip of the iceberg, with more problems concealed elsewhere.
03The bay-window junction and external cracking
The built-up junction exposed behind the trim and cracking beside the bay raise a possible structural integrity concern requiring further investigation. This should cover both ends, the fixings, any load-bearing support, and the survey and installation detail.
04Deterioration and the risk of further damage
A small number of issues appeared after T&K stopped work, leaving the installation unfinished. Some have worsened over time. I’m concerned about water ingress and further property damage, and want the affected work assessed and put right.
05No compliance certificate supplied
I have not been supplied with an Assure or equivalent Building Regulations compliance certificate for this installation. The DGCOS insurance paperwork is a different document.
06Windows and doors that worked properly
I raised problems with opening, closing, alignment, seals and finishes. These were the everyday details I wanted checked and put right.
07A clear plan to finish
I wanted to know what each return visit would achieve and what would still be left afterwards. My account is that we never reached an agreed final sign-off.
08Damage made good
My emails raised damage to surfaces, plaster, render, decoration, tiles and belongings. I wanted the damage addressed alongside the installation.
09A payment position I could understand
I made an agreed payment in May 2024 while work continued. I later challenged the invoice and remaining balance. The exact payment reconciliation is still unresolved.
10Confidence in the guarantee
If another installer has to finish or rectify the work, what protection will I have? I want that answered clearly, alongside the written guarantee and compliance certification.
11Care while working in our home
My January 2024 email also raised concerns about doors being left unsecured and keys being unavailable. These concerns relate to that period, not our home’s current security.